1 Preliminary design - 2 main body demolition - 3 hydropower reform - 4 carpentry - 5 tiling - 6 brush wall paint - 7 kitchen ceiling - 8 cabinet installation - 9 wooden door installation - 10 floor Installation - 11 paving wallpaper - 12 radiator installation - 13 switch socket installation - 14 lighting installation - 15 hardware sanitary fixture - 16 curtain rod installation - 17 pioneer cleaning - 18 furniture approach - 19 Appliance Installation - 20 Home Accessories
Shen Huang solid wood furniture
Renovation is basically done in accordance with these 20 steps. In the following, I will try my best to explain the decoration process that I know so far as well as the details that need attention in the whole process....
First, the whole process of renovation of 20 links
(I) Pre-design
In the same way, the difference between humans and bees is that the construction of bees is a reflection of instincts. Before humans are built, ideas and frameworks are first formed in the mind. Therefore, if the home improvement compared to a battle, then the pre-design home improvement is the battle of the "war plan" is the home improvement "soul link."
In the early design, one of the things that the classmates must do is to make a detailed measurement of their own room. Don't be lazy. It's best to measure it yourself. The measurement includes:
1. Identify the area involved in the renovation process. Especially the tiling area, wall paint area, wallpaper area, floor area;
2, clear the main wall size. In particular, it is necessary to design the wall size of the furniture later.
I remember that when my foreman at last told me to lay out the total amount of bricks according to the “actual amountâ€, he measured 10 square meters more than the area I measured. I was really dumbfounded. After re-measurement, the foreman returned to reprimanding the bricklayer and said: "How do you measure?!" This is why I suggest that you measure yourself. Many places are decorated with the same reason as human beings - we don't necessarily understand it, but we must have a few.
Remind everyone, do not forget to go to the property before the start of construction formalities, pay a decoration deposit.
(II) Demolition of the main body
Into the construction phase, the main demolition reform is the first project on the first, mainly including the demolition of walls, walls, spade shovel, demolition heating, change steel windows and so on. When the main body is dismantled and reformed, it is to put the framework of the construction site first.
(III) Hydropower Reform
Before the transformation of the water circuit, the demolition of the main structure should be basically completed. Between the two stages of hydropower reform and main body demolition and reform, some students may know that the first measurement of cabinets should also be conducted. In fact, the so-called cabinet first measurement has no actual content, because the wall and the ground are not processed, the cabinet designer can not give a specific design size, but only for the developer reserved water inlet, hood socket Location, make some suggestions. mainly include:
1. Check if the position of the socket outlet affects the installation of the hood in the future;
2, see if the location of the water meter is appropriate;
3, see if the position of the inlet is convenient for installing the sink later
For the first measurement of the cabinet, slightly experienced students can do it completely. After the waterway is completed, it is best to do the waterproofing of the bathroom. The kitchen does not generally need to be waterproof.
Some students have always thought that before the renovation began, some main materials should be advanced. What I want to say is that, unless it is the main material needed for the demolition of the main body, the entry time of main materials such as tiles and large core boards should be after the hydropower reform. Because the circuit modification involves ground slotting, if tiles or large core boards are improperly positioned, it is troublesome for workers to move in and out. Two days ago, the "rat" classmate also told me that her family had encountered the problem of the workers returning from the room full of bricks, reminding the students to pay attention.
(d) Woodworking
Carpenters, bricklayers, and oil workers are the "three brothers" in the construction process. The basic order of appearance is: wood-tile-oil. The basic appearance principle is - who is dirty and who is the first. "Who is dirty? Whoever is above" is also one of the basic principles that determine the order of home improvement. I will mention it later. In fact, carpentry activities such as installing standpipes, making decorative ceilings, and attaching plaster lines can be considered in a sense as a detailed link of the main demolition and reform. They themselves do not conflict with the transformation of water circuits, and sometimes they still need some. Cooperation, as mentioned in my last post, “If you are preparing to make a false wall at home, consider whether there is a hydropower circuit on the false wall. If there are, you should let the hydropower reform workers pre-manage.â€
(five) tiling
If the workers are too busy, the foreman will normally allow the bricklayer to enter the tiling when the “wooden boss†is not over. This is normal, because there is no conflict between the two.
In the process of “bricklayerâ€, the following three steps are also involved:
1. The installation of door stone and marble windowsill. The installation of the door stone can be done together with the paving tiles, or after the paving tiles, the installation of the marble window sill is usually done after the window cover is done. The marble worker will prepare the glass glue, and the marble and the window cover are sealed with glass glue. Now.
2, the installation of floor drain. The floor drain is the first one to appear in the home improvement hardware because it needs to be installed together with the floor tile. Therefore, when the students started to visit the building materials, they should buy land drains as early as possible.
3, hood installation. The hood is the first appearance of the appliance. After the kitchen tiles are laid, you can consider installing the hood.
“The bricklayer's second cousin†leaves the floor. At this time, the cabinet can be measured for the second time. Accurately speaking, after the wall tiles have been attached and the hood is installed, the second measurement of the cabinet can be performed.
(six) brush wall paint
The “oil worker's third child†entered the field and mainly completed the work of basic wall surface treatment, brush finish, and painting of furniture hit by the “wooden bossâ€. To prepare wallpapers for students, you only need to let the “oil worker†in the plan to do wallpaper on the wall. As for whether or not to stay in the paint for the last time, I personally feel that this problem is not necessarily too true. From the experience of my renovation, the significance of leaving the paint once again is not great, because the operation behind it is no more messy than painting. . [Page] wrote here, dead resistance when the "boss", "second child", "third child" have left the field, many students will think that their decoration is almost over, in fact, according to the number of links, one-third Not yet. The reason why everyone has this feeling is that people generally understand the decoration is only the decoration of the "construction part", in fact, the decoration of the "installation link" is also the focus of decoration. If the "design link" is to "conceive" the look of our future home, then the "construction link" is to "package" our home, and really say that "home-made" homes are almost all in the "installation phase." Drink saliva and continue...
Decoration Start-up Preparation Renovation Process Confucius Decorating Lacquer Wood Doors & Windows Decoration Design Home Improvement Decoration Looking For Decoration Company Home Wallpaper Glass Tile Cabinet Door Marble Tile Kitchen & Bathroom Ceiling Household Cabinetry Glass Glass Furniture Marble Cabinet Kitchen Cabinet Door Floor Tile Glass Door Kitchen Glass Sliding Door Bathroom Tiles Bathroom Doors Bathroom Ceiling Material Bathroom Door Size Bathroom Size Toilet Design Toilet Ceiling Overall Toilet Public Toilet Toilet Waterproof Bathroom Floor Tile Toilet Leakage Home Decoration Home Tile Glue Kitchen Tile ld Tile Floor Tile Decoration Home
Led Area Light,200W Led Area Light,Led High Area Light,Dlc Area Lights
Fuonce-Lighting , https://www.fuoncelighting.com